Cirbus Lane line replacementUpdated: April 10, 2019 - 1:11pm replacing 675 feet of 3 inch cast iron pipe with 6 inch iron ductile pipe.Read more |
Noel Drive @ HochbergUpdated: March 19, 2019 - 10:16am Replacement of 6 inch cast iron water line with 6 inch iron ductile pipe Expected completion April 30, 2019Read more |
2018 Sanitary Sewer Rehabilitation ProjectUpdated: January 28, 2019 - 2:28pm The Monroeville Municipal Authority (MMA) will begin a sanitary sewer rehabilitation project on June 19, 2018. Approximately 40,000 linear feet of structurally deficient sanitary sewer line will be rehabilitated by relining. Various neighborhoods in Monroeville will be affected. Contractors working...Read more |
Restore Water BreaksUpdated: March 19, 2018 - 4:18pm Restoration from winter water breaksRead more |
Water Line Replacement -Rt22 to Kenmar DriveUpdated: October 12, 2017 - 10:37am replacement of an eight inch water line from rte 22 to Kenmar Drive. Estimated project duration: 5 weeksRead more |
Valve replacements- Mosside Blvd @ Daugherty DrUpdated: October 12, 2017 - 10:36am Replacement of 12 inch valves on Mosside Boulevard at Daugherty Drive.Read more |
Center Road waterline replacementUpdated: October 12, 2017 - 10:36am 8 inch waterline replacement on Center Road from My Way to KenmarRead more |
Tilbrook RoadUpdated: September 8, 2017 - 2:50pm Water line installation on Tillbrook Road.Read more |
2017 MMA Sewer Lining Rehabilitation ContractUpdated: August 28, 2017 - 9:16am Insight Pipe Contracting, LLC will be cleaning, televising, and relining approximately 8,500 linear feet of 8 to 15-inch diameter sanitary sewer line within the MMA service area. Partial funding for this project is being provided through a PA Small Water and Sewer Grant in the amount of $92,000...Read more |
Feb/March 2017Updated: May 16, 2017 - 12:28pm Maintenance of Sewers- Garden City Area Line Replacement Projects- Williamsburg Drive & Tilbrook RoadRead more |