All Project Status Updates

  • Updated: 1 day 14 hours ago
    Water line installation on Tillbrook Road. Completion Date: Mid August 2017

    Status Update:

    new water line installation has begun
  • Updated: 1 month 1 week ago
    Replacement of 12 inch valves on Mosside Boulevard at Daugherty Drive.

    Status Update:

    hours of construction: after 10:00pm
  • Updated: 1 month 1 week ago
    replacement of an eight inch water line from rte 22 to Kenmar Drive. Estimated project duration: 5 weeks

    Status Update:

    project started
  • Updated: 4 months 3 weeks ago
    Maintenance of Sewers- Garden City Area Line Replacement Projects- Williamsburg Drive & Tilbrook Road

    Status Update:

    5/16/2017 project complete
  • Updated: 1 year 1 month ago
    On May 5, 2016, final connections will be made to the new 10-inch ductile iron pipe installed between Revere Drive and 423...

    Status Update:

    5/10/16- Work is done. Paving will be done in August.
  • Updated: 1 year 1 month ago
    Starting late May, the crew will be installing 2300 feet of ductile iron pipe from Tyrolia to Dolomite, Dolomite to Alpine...

    Status Update:

    Water taps & water line work is complete on Cavitt/Dolomite. Paving will begin on Monday, Sept 19- please refrain from parking on the street.

For questions or to report problems: 412-372-2677